USE CASE 020.FFM.L3.01 REAL PROPERTY: STEWARDSHIP LAND, HERITAGE ASSETS, CONSTRUCTION, AND IMPAIRMENT |
---|
Typical Flow of Events |
---|
|
FFM Event |
Non-FFM Event |
Input(s) |
Output(s) / Outcome(s) |
---|
1 |
|
- Develop specifications for construction of additional structure
(PRM.020.020 Property Space Design and Construction)
- Prepare and submit purchase request for construction of additional structure
(ACQ.020.010 Procurement Request (PR) Processing)
- Request funds availability check
(ACQ.020.010 Procurement Request (PR) Processing)
|
- Property title
- Additional structure functional needs
|
- Specifications for construction of additional structure
- Submitted purchase request for construction of additional structure
- Request for funds availability check
|
---|
2 |
Receive and process request for status of funds availability (FFM.010.020 Fund Allocation and Control) |
|
- Request for funds availability check
|
- Funds availability response
|
---|
3 |
|
Approve purchase request (ACQ.020.010 Procurement Request (PR) Processing) |
- Funds availability response
- Submitted purchase request for construction of additional structure
|
- Approved purchase request for construction of additional structure
|
---|
4 |
Receive approved purchase request for construction of additional structure and commit funds (FFM.030.020 Obligation Management) |
|
- Approved purchase request for construction of additional structure
|
- Appropriate commitment entry created with reference to source information
|
---|
5 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
6 |
|
- Develop solicitation for construction of additional structure
(ACQ.020.080 Solicitation Documentation Development)
- Issue solicitation
(ACQ.020.100 Solicitation Issuance)
- Receive vendors’ responses to solicitation and evaluate responses
(ACQ.030.010 Proposal Evaluation)
- Select a vendor
(ACQ.030.060 Award Decision)
- Develop order or award for that vendor for construction of additional structure
(ACQ.030.070 Contract Award Issuance)
- Request funds availability check
(ACQ.030.070 Contract Award Issuance)
|
- Specifications for construction of additional structure
- Approved purchase request for construction of additional structure
- Approved acquisition schedule
- Vendor responses to solicitation
|
- Solicitation
- Selected vendor
- Order or award information for construction of additional structure
- Request for funds availability check
|
---|
7 |
Receive and process request for funds availability check (FFM.010.020 Fund Allocation and Control) |
|
- Request for funds availability check
|
- Funds availability response
|
---|
8 |
|
Approve and issue order or award for construction of additional structure (ACQ.030.070 Contract Award Issuance) |
- Order or award information for construction of additional structure
- Funds availability response
|
- Approved order or award for construction of additional structure
|
---|
9 |
Receive approved order or award information, confirm difference between obligation amount and commitment amount does not exceed tolerance percentage/amount, obligate funds, and liquidate commitment (FFM.030.020 Obligation Management) |
|
- Approved order or award for construction of additional structure
|
- Appropriate obligation entry created with reference to source information
- Appropriate commitment liquidation entry created with reference to source information
|
---|
10 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
11 |
|
- Receive vendor invoice information for site preparation costs in an OMB-approved electronic invoicing solution
- Provide notification of vendor invoice submission for review and acceptance of vendor invoice for site preparation costs
(ACQ.040.020 Documentation of Delivery/Acceptance)
|
- Vendor invoice for site preparation costs
- Receiving report, if used
- Approved order or award for construction of additional structure
|
- Notification of vendor invoice submission
- Accepted vendor invoice for site preparation costs
|
---|
12 |
Receive and process accepted vendor invoice for site preparation costs from OMB-approved electronic invoicing solution and perform a three-way match (FFM.030.070 Payment Processing - Commercial Payments) |
|
- Accepted vendor invoice for site preparation costs
- Receiving report, if used
- Approved order or award
|
- Successful three-way match
- Appropriate payable entry created with reference to source information
- Validated vendor invoice for site preparation costs
|
---|
13 |
|
Request funds availability check (ACQ.040.020 Documentation of Delivery/Acceptance) |
- Validated vendor invoice for site preparation costs
|
- Request for funds availability check
|
---|
14 |
Receive and process request for funds availability check (FFM.010.020 Fund Allocation and Control) |
|
- Request for funds availability check
|
- Funds availability response
|
---|
15 |
|
- Approve vendor invoice for site preparation costs
- Request for processing of approved vendor invoice
(ACQ.040.020 Documentation of Delivery/Acceptance)
|
- Funds availability response
- Validated vendor invoice for site preparation costs
|
- Approved vendor invoice for site preparation costs
- Request for processing of approved vendor invoice
|
---|
16 |
- Receive and process approved vendor invoice (FFM.030.070 Payment Processing - Commercial Payments)
- Confirm difference between expenditure amount and obligation amount does not exceed tolerance percentage/amount (FFM.030.020 Obligation Management)
- Establish payable (FFM.030.070 Payment Processing – Commercial Payments)
- Liquidate obligation (FFM.030.020 Obligation Management)
|
|
- Approved vendor invoice
- Request for processing of approved vendor invoice
|
- Appropriate payable entry created with reference to source information
- Appropriate obligation liquidation entry created with reference to source information
- Appropriate accrual reversal entry created with reference to source information
|
---|
17 |
|
Request for disbursement (ACQ.040.020 Documentation of Delivery/Acceptance) |
|
|
---|
18 |
- Receive and process disbursement request
(FFM.030.070 Payment Processing – Commercial Payments)
- Initiate disbursement
(FFM.030.070 Payment Processing - Commercial Payments)
- Generate disbursement schedule
(FFM.030.110 Payment Disbursement)
- Certify payment of disbursement schedule
(FFM.030.110 Payment Disbursement)
- Receive confirmation of disbursement
(FFM.030.120 Payment Confirmation)
|
|
|
- Appropriate payable entry liquidated with reference to source information
- Appropriate disbursement-in -transit entry created with reference to source information
- Certified disbursement schedule
- Disbursement confirmation information
- Appropriate disbursement entry created with reference to source information
- Vendor receives payment
|
---|
19 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
20 |
|
- Adjusted cost for stewardship land information to reflect site preparation
(PRM.010.050 Property Valuation)
- Request processing of stewardship land asset information
(PRM.010.070 Property Acquisition and Control Reporting)
|
- Stewardship land asset information
- Current stewardship land property record
- Site preparation costs
|
- Stewardship land asset information
- Adjustments to stewardship land asset description
- Updated property record for stewardship land
- Request to process updated stewardship land asset information
|
---|
21 |
Receive and process updated stewardship land asset information (FFM.020.030 Financial Asset Information Processing - Heritage Assets and Stewardship Land) |
|
- Request to process updated stewardship land asset information
|
- Appropriate entries for stewardship land asset information updated with reference to source information
|
---|
22 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
23 |
|
- Determine capitalization of construction costs and government labor costs for construction management
(PRM.010.050 Property Valuation)
- Determine asset value of work-in-progress construction asset for additional structure
(PRM.010.050 Property Valuation)
- Establish property record for work-in-progress construction asset for additional structure
(PRM.010.060 Property Control and Accountability)
- Request establishment of work-in-progress construction asset information for additional structure
(PRM.010.070 Property Acquisition and Control Reporting)
|
- Approved order or award for construction of additional structure
- Estimated government labor costs for construction management
|
- Capitalized construction costs and construction management labor costs for the additional structure
- Asset value of work-in-progress construction asset for additional structure
- Work-in-progress construction asset property record for additional structure
- Request to establish work-in-progress construction asset information for additional structure
|
---|
24 |
Receive and process request to establish work-in-progress construction asset information for additional structure (FFM.020.010 Financial Asset Information Processing - Property, Plant, and Equipment) |
|
- Request to establish work-in-progress construction asset information for additional structure
|
- Appropriate entries for work-in-progress construction asset information for additional structure created with reference to source information
|
---|
25 |
Post appropriate budgetary, proprietary and memorandum entries to the general ledger (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
26 |
|
- Receive monthly vendor invoice information for construction costs in an OMB-approved electronic invoicing solution
- Provide notification of monthly vendor invoice submission for review and acceptance of vendor invoice for construction costs
(ACQ.040.020 Documentation of Delivery/Acceptance)
|
- Monthly vendor invoice for construction costs
- Receiving report, if used
- Approved order or award for construction of additional structure
|
- Notification of monthly vendor invoice submission
- Accepted monthly vendor invoice for construction costs
|
---|
27 |
- Receive accepted monthly vendor invoice for construction costs from OMB-approved electronic invoicing solution and perform a three-way match
(FFM.030.070 Payment Processing - Commercial Payments)
- Revalue work-in-progress construction asset information
(FFM.020.010 Financial Asset Information Processing - Property, Plant, and Equipment)
|
|
- Accepted monthly vendor invoice for construction costs
- Receiving report, if used
- Approved order or award for construction of additional structure
|
- Successful three-way match
- Appropriate payable entry created with reference to source information
- Appropriate work-in-progress construction asset information for additional structure entry created with reference to source information
- Validated monthly vendor invoice for construction costs
|
---|
28 |
|
Request funds availability check (ACQ.040.020 Documentation of Delivery/Acceptance) |
- Validated monthly vendor invoice for construction costs
|
- Request for funds availability check
|
---|
29 |
Receive and process request for funds availability check (FFM.010.020 Fund Allocation and Control) |
|
- Request for funds availability check
|
- Funds availability response
|
---|
30 |
|
- Approve monthly vendor invoice for construction costs
- Request for processing of approved vendor invoice
(ACQ.040.020 Documentation of Delivery/Acceptance)
|
- Funds availability response
- Validated vendor invoice for construction costs
|
- Approved monthly vendor invoice for construction costs
- Request for processing of approved vendor invoice
|
---|
31 |
- Receive and process approved vendor invoice (FFM.030.070 Payment Processing - Commercial Payments)
- Confirm difference between expenditure amount and obligation amount does not exceed tolerance percentage/amount (FFM.030.020 Obligation Management)
- Establish payable (FFM.030.070 Payment Processing – Commercial Payments)
- Liquidate obligation
(FFM.030.020 Obligation Management)
|
|
- Approved vendor invoice
- Request for processing of approved vendor invoice
|
- Appropriate payable entry created with reference to source information
- Appropriate obligation liquidation entry created with reference to source information
- Appropriate accrual reversal entry created with reference to source information
|
---|
32 |
|
Request disbursement (ACQ.040.020 Documentation of Delivery/Acceptance) |
|
|
---|
33 |
- Receive and process disbursement request
(FFM.030.070 Payment Processing – Commercial Payments)
- Initiate disbursement
(FFM.030.070 Payment Processing - Commercial Payments)
- Generate disbursement schedule
(FFM.030.110 Payment Disbursement)
- Certify payment of disbursement schedule
(FFM.030.110 Payment Disbursement)
- Receive confirmation of disbursement
(FFM.030.120 Payment Confirmation)
|
|
|
- Appropriate payable entry liquidated with reference to source information
- Appropriate disbursement-in -transit entry created with reference to source information
- Certified disbursement schedule
- Disbursement confirmation information
- Appropriate disbursement-in -transit entry liquidated with reference to source information
- Appropriate disbursement entry created with reference to source information
- Vendor receives payment
|
---|
34 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
35 |
|
- Hazardous substances are discovered on the property and a hazard substance report is prepared
(PRM.010.070 Property Acquisition and Control Reporting)
- Modify contract to stop work due to hazardous materials
(ACQ.040.030 Contract Modification)
- Request deobligation of remaining contract funds
(ACQ.040.030 Contract Modification)
- Complete an asset impairment review
(PRM.010.070 Property Acquisition and Control Reporting)
|
- Discovery of hazardous materials on construction site
|
- Hazard substances report
- Stop work order contract modification
- Request for deobligation of remaining contract funds
- Asset impairment review
|
---|
36 |
Receive and process request for deobligation of remaining contract funds (FFM.030.020 Obligation Management) |
|
- Request for deobligation of remaining contract funds
|
- Appropriate deobligation entry created with reference to source information
|
---|
37 |
|
- Request vendor submit final invoice
(ACQ.040.030 Contract Modification)
- Receive final vendor invoice information in an OMB-approved electronic invoicing solution
(ACQ.040.020 Documentation of Delivery/Acceptance)
- Provide notification of vendor final invoice submission for review and acceptance of final vendor invoice
(ACQ.040.020 Documentation of Delivery/Acceptance)
|
- Final vendor invoice
- Receiving report, if used
- Approved order or award for additional structure
|
- Request for submission of final vendor invoice
- Notification of vendor final invoice submission
- Accepted final vendor invoice
|
---|
38 |
Receive accepted final vendor invoice from OMB-approved electronic invoicing solution and perform a three-way match (FFM.030.070 Payment Processing - Commercial Payments) |
|
- Accepted final vendor invoice
- Receiving report, if used
- Approved modified order or award for additional structure
|
- Successful three-way match
- Appropriate payable entry created with reference to source information
- Validated final vendor invoice
|
---|
39 |
|
Request funds availability check (ACQ.040.020 Documentation of Delivery/Acceptance) |
- Validated final vendor invoice
|
- Request for funds availability check
|
---|
40 |
Receive and process request for funds availability check (FFM.010.020 Fund Allocation and Control) |
|
- Request for funds availability check
|
- Funds availability response
|
---|
41 |
|
- Approve final vendor invoice
- Request for processing of approved vendor invoice
(ACQ.040.020 Documentation of Delivery/Acceptance)
|
- Funds availability response
- Validated final vendor invoice
|
- Approved final vendor invoice
- Request for processing approved vendor invoice
|
---|
42 |
- Receive and process approved vendor invoice (FFM.030.070 Payment Processing - Commercial Payments)
- Confirm difference between expenditure amount and obligation amount does not exceed tolerance percentage/amount (FFM.030.020 Obligation Management)
- Establish payable (FFM.030.070 Payment Processing – Commercial Payments)
- Liquidate obligation
(FFM.030.020 Obligation Management)
|
|
- Approved vendor invoice
- Request for processing of approved vendor invoice
|
- Appropriate payable entry created with reference to source information
- Appropriate obligation liquidation entry created with reference to source information
- Appropriate accrual reversal entry created with reference to source information
|
---|
43 |
|
Request disbursement (ACQ.040.020 Documentation of Delivery/Acceptance) |
|
|
---|
44 |
- Receive and process disbursement request
(FFM.030.070 Payment Processing – Commercial Payments)
- Initiate disbursement
(FFM.030.070 Payment Processing - Commercial Payments)
- Receive and Generate disbursement schedule
(FFM.030.110 Payment Disbursement)
- Certify payment of disbursement schedule
(FFM.030.110 Payment Disbursement)
- Receive confirmation of disbursement
(FFM.030.120 Payment Confirmation)
|
|
|
- Appropriate payable entry liquidated with reference to source information
- Appropriate disbursement-in -transit entry created with reference to source information
- Certified disbursement schedule
- Disbursement confirmation information
- Appropriate disbursement-in -transit entry liquidated with reference to source information
- Appropriate disbursement entry created with reference to source information
- Vendor receives payment
|
---|
45 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
46 |
|
- Determine asset value for partially completed structure due to construction abeyance
(PRM.010.050 Property Valuation)
- Update property record, if needed, for additional structure asset to reflect revaluation from partial completion
(PRM.010.060 Property Control and Accountability)
- Request processing of revised asset information and write off of difference between prior and impaired asset value for additional structure, if a difference exists
(PRM.010.070 Property Acquisition and Control Reporting)
|
- Work-in-progress construction asset information
- Current property record
|
- Revised asset valuation for partially completed structure
- Updated property record for additional structure asset to reflect revaluation from partial completion
- Request to process revised asset information and write off of difference between prior and impaired asset value for additional structure
|
---|
47 |
Receive and process revised asset information and write off of difference between prior and impaired asset value for additional structure (FFM.020.010 Financial Asset Information Processing - Property, Plant, and Equipment) |
|
- Request to process revised asset information and write off of difference between prior and impaired asset value for additional structure
|
- Appropriate property asset entries updated with reference to source information
- Appropriate loss entry created with reference to source information
|
---|
48 |
Post appropriate budgetary, proprietary, and/or memorandum entries to the general ledger (GL) (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|
49 |
|
- Update property records for stewardship land and heritage asset to reflect impairment of new construction (PRM.010.060 Property Control and Accountability)
- Request capture of updated stewardship land and heritage asset information (PRM.010.070 Property Acquisition and Control Reporting)
|
- Property title
- Asset impairment review
- Stewardship land and heritage asset information
- Current property record
|
- Revised stewardship land and heritage asset description
- Updated property records for stewardship land and heritage asset
- Request to capture stewardship land and heritage asset information
|
---|
50 |
Receive and process request to capture stewardship land and heritage asset information (FFM.020.030 Financial Asset Information Processing - Heritage Assets and Stewardship Land) |
|
- Request to capture stewardship land and heritage asset information
|
- Appropriate entries for stewardship land and heritage asset information updated with reference to source information
|
---|
51 |
Post appropriate budgetary, proprietary and/or memorandum entries to the general ledger (FFM.090.020 General Ledger Posting) |
|
|
- Appropriate GL accounts updated
|
---|